Construction Update
CASA CANAL
Dubai Water Canal
We are delighted to provide you with an update on the progress of Casa Canal, to showcase the milestones achieved and anticipated developments ahead.
PROGRESS REPORT
CASA CANAL
PROGRESS STATUS

Design
Concept Design
Completed
Shoring Design
Completed
Schematic Design
Completed
Piling Design
Completed
Detailed Design
Completed

Procurement
Shoring Contractor
Appointed
Piling Contractor
Appointed
Main Works Contractor
Appointed
MEP Contractor
Appointed
Facade Contractor
Appointed
Fit Out Contractor
Appointed

Authority
Preliminary Design Approval
Obtained
Design NOC's Approval
Obtained
Site Clearance NOC's
Obtained
Shoring Permit
Obtained
Piling Permit
Obtained
Building Permit
Obtained

Siteworks
Shifting Existing Services from Plot
Completed
Shoring Works
Completed
Piling Works
Completed
Excavation Works
Completed
Foundation Works
Completed
BASEMENTS SLAB (B3,B2,B1)
Completed
GROUND FLOOR SLAB- LEVEL 13 SLAB
Completed
LEVEL 14 FLOOR SLAB
IN PROGRESS
BLOCKWORK & PLASTER
In Progress
MEP WORKS
In Progress
ALUMINUM GLAZING & GRC WORKS
In Progress
Updated Timeline

Shoring Works
Completed
Piling and Enabling
Completed
Foundation Works
Completed
Substructure Works
Completed
Superstructure Works
Q4 2026
External Glass Works
Q2 2027
MEP and Finishes Work
Q3 2027
Handover
Q3 2027
Thank You
For being part of this exciting journey