Construction Update

CASA CANAL

Dubai Water Canal

We are delighted to provide you with an update on the progress of Casa Canal, to showcase the milestones achieved and anticipated developments ahead.

PROGRESS REPORT

CASA CANAL

PROGRESS STATUS

Casa Canal facade design at golden hour

Design

Concept Design

Completed

Shoring Design

Completed

Schematic Design

Completed

Piling Design

Completed

Detailed Design

Completed

Casa Canal facade detail with sculpted balconies

Procurement

Shoring Contractor

Appointed

Piling Contractor

Appointed

Main Works Contractor

Appointed

MEP Contractor

Appointed

Facade Contractor

Appointed

Fit Out Contractor

Appointed

Casa Canal tower overlooking the Dubai Water Canal

Authority

Preliminary Design Approval

Obtained

Design NOC's Approval

Obtained

Site Clearance NOC's

Obtained

Shoring Permit

Obtained

Piling Permit

Obtained

Building Permit

Obtained

Casa Canal balconies and colonnade at sunset

Siteworks

Shifting Existing Services from Plot

Completed

Shoring Works

Completed

Piling Works

Completed

Excavation Works

Completed

Foundation Works

Completed

BASEMENTS SLAB (B3,B2,B1)

Completed

GROUND FLOOR SLAB- LEVEL 13 SLAB

Completed

LEVEL 14 FLOOR SLAB

IN PROGRESS

BLOCKWORK & PLASTER

In Progress

MEP WORKS

In Progress

ALUMINUM GLAZING & GRC WORKS

In Progress

Updated Timeline

Casa Canal facade nearing completion, sculpted balconies at golden hour

Shoring Works

Completed

Piling and Enabling

Completed

Foundation Works

Completed

Substructure Works

Completed

Superstructure Works

Q4 2026

External Glass Works

Q2 2027

MEP and Finishes Work

Q3 2027

Handover

Q3 2027

Thank You

For being part of this exciting journey